How long does a DA take in NSW? The stages, the timeframes and what they mean for trades

From lodgement to approval to the first day on site: the stages a NSW development application goes through, the legal timeframes, why real assessment times vary so much, and the best moment for each trade to make contact.

The LodgedLeads team · · 4 min read

“How long will council take?” is the first question most owners ask after lodging a development application, and the honest answer is: it depends. But the process follows the same stages every time, and once you know them, a DA’s status tells you a lot about where a project is up to, and when the trades will be needed.

The stages of a NSW development application

  1. Lodgement. The applicant, usually the owner, their builder or a planning consultant, lodges the application online through the NSW Planning Portal with plans, reports and fees. Council checks it is complete before formally accepting it.
  2. Notification. Many applications are notified to neighbours or placed on public exhibition so people can comment. Each council sets its own rules in its community participation plan; for many local applications the period is around 14 days.
  3. Assessment. A council planner assesses the proposal against the planning controls for the site, may refer it to other agencies (for example for bushfire, heritage or water), and often asks the applicant for more information or amended plans.
  4. Determination. The application is approved, usually with conditions, or refused. Larger or contentious applications may go to a local planning panel.
  5. Before building starts. Approval is not the same as permission to start work. For building work the owner generally needs a construction certificate, appoints a principal certifier and gives notice before work begins. Only then does the site get busy.

What the law says about timeframes

NSW planning law sets an assessment period after which an applicant can treat an undetermined application as refused, which lets them appeal to the Land and Environment Court. For most development applications that period is 40 days, and it is longer for some types, such as applications that need approvals from other agencies.

That is not a deadline councils must meet. Applications regularly take longer than 40 days, especially when council asks for more information, the plans change, or neighbours object. The clock gives a right of appeal, not a promise.

How long it really takes

Real-world times vary widely between councils, between types of development, and with how complete the application was when it went in. A straightforward pool or alterations application at a well-resourced council can be decided in a few weeks; a new house on a sloping, bushfire-prone or heritage site, or a multi-unit development, can take many months.

The NSW Government publishes assessment-time figures for councils, so owners and builders can see how their council compares. If you work mainly in two or three council areas, it is worth knowing roughly how long each one takes, because it tells you how far ahead your pipeline really runs.

A DA’s status is a project’s clock. Lodged means early planning; approved means work is close.

Modifications and reviews

Approval is not always the end of the paperwork. If the owner wants to change an approved design (a bigger window, a different pool position, an extra room) they lodge a modification application. In the NSW Planning Portal data we read, roughly one in five applications is a modification. If an applicant disagrees with council’s decision, they can also ask for a review of determination.

Modifications are worth watching. They usually mean a project is real and moving, and sometimes they add exactly the work your trade does.

What each stage means for trades

  • Just lodged. The project is at its earliest. Builders and the trades that shape the design, such as pool builders, landscapers, solar and electrical, can still influence what gets built. This is the best moment to introduce yourself.
  • Under assessment or more information requested. The owner is waiting on council and often comparing prices. A clear, written quote with the application number on it stands out.
  • Approved. Construction is close, usually within months, once the construction certificate is sorted. This is the moment for the trades that come in during the build: demolition, excavation, concreting, framing, roofing, plumbing, fencing.
  • Refused. Not always the end. Applicants often redesign and lodge again, or seek a review.

Consents also don’t last forever. A development consent generally lapses if work hasn’t physically started within five years, so an old approval with no activity is a weaker lead than a fresh one.

How LodgedLeads tracks the clock for you

LodgedLeads checks the NSW Planning Portal every 15 minutes and emails you each new application that matches your trades and area the evening it is lodged. You can also tick “tell me when a matching application is approved”, so you hear again at the moment work can start, the best time to quote for the build-stage trades. Your Monday summary lists what was approved in your area that week.

Every lead shows its current status, and your account links to the council’s own tracker, where you can read the plans and follow the assessment. See what’s moving now on the latest applications page, or start a 14-day free trial with no credit card. If you’re wondering why some jobs never show up as a DA at all, read DA vs CDC in NSW.

This article is general information about the NSW planning process, not legal or planning advice. Rules differ between types of development and councils; the NSW Planning Portal and your council have the details for a particular site.